Pre-solicitationPosted Jun 2, 2026·Responses due Jun 18, 2026

NOS NCCOS COOP Oxford Lab BSL-2 Project

NOAA · DEPT OF COMMERCE NOAA

Stage
Early notice (sources sought, presolicitation or special notice)
NAICS
236220
Value
Not stated
Solicitation
1305M426R0030
Set-aside
Small Business Set Aside - Total
PSC
Y1DB
Place
Oxford, MD, USA
Contact
Noelle Albert (noelle.albert@noaa.gov)
CSV Email

Capture briefs (a one-page, shareable copy of this page) are part of Pro. The CSV here holds the notice, its timeline and past awards.

Where this opportunity stands

Every notice posted under solicitation 1305M426R0030 in this department, oldest first.

Early notice
  • Jun 2, 2026
    Pre-solicitation
    Open
  • Jun 2, 2026 · this notice
    Pre-solicitation
Solicitation
  • Jun 18, 2026
    Solicitation
    Open
  • Jul 15, 2026
    Solicitation
    Open
  • Jul 20, 2026
    Solicitation
    Open
  • Jul 29, 2026
    Solicitation
    Open
Award
  • Sep 8, 2026
    Award Notice
    J G M PROPERTY GROUP, INC. · $815K
    Open

Next steps for this stage

Standard steps for the notice type; not advice about this buyer.

  • Answer the notice: this is when the requirement can still be shaped.
  • Contact the contracting officer named on the notice.
  • Check who won similar work; they are the likely bidders.

What the notice says

Project Description - Construction: Generally described as follows but not limited to: This award covers construction at one site under one period of performance, organized as a base scope (CLIN 0001) and optional scopes (CLIN 0002, CLIN 0003, and CLIN 0004). The Contractor shall coordinate trades and logistics to minimize disruption to NOAA operations. CLIN 0001 - New BSL-2 Laboratory, Equipment Relocation, and Trailer Decommissioning (Base) CLIN 0002 - New Conference Room (Option) CLIN 0003 - Equipment Vestibule (Option) CLIN 0004 - Laboratory Fume Hood and DI Water System (Option) The scope… (show all)

of services includes all supervision, licensed design, engineering, labor, materials, permits, documentation, fabrication, and installation requirements shown or implied by this SOW and its attachments. Work includes, but is not limited to, demolition, concrete, architectural, structural, roofing, mechanical, electrical, plumbing (MEP), heating, ventilation, and air conditioning (HVAC), and fire protection systems. The Contractor is responsible for verifying existing conditions and developing the Government's reference documents into permit-ready construction documents. Before acceptance of each CLIN, the Contractor shall conduct a 1�2 hour walkthrough with Owner laboratory and facilities staff covering room layout, operation of doors, HVAC controls, emergency equipment (eyewash, sink, safety shower if applicable), and locations of panels and shutoffs. The Contractor shall provide an electronic closeout package including final layout drawings, as-built drawings (PDF), manuals and warranty information, test reports (eyewash, HVAC/airflow, hood/enclosure checks, electrical inspections), and a final cost breakdown by trade in Excel. The Contractor shall provide a one-year warranty on workmanship and Contractor-supplied materials, starting upon NOAA's written acceptance. This is a new requirement for construction services for the Oxford Maryland facility. RFO 36.101-4 Advance notices and solicitations requires agencies to provide a description of policies and procedures that apply to the definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. The Department of Commerce (DOC) does not publish this information at this time. NOAA aims to definitize change orders no later than 30 days after reviewing and negotiating anticipated costs from the contractor's change order proposal. Site Visit Information: Offerors will have the opportunity to visit the site before submission of their technical and price proposals. The site visit details, to be held at the Oxford, MD Facility, will be outlined in the solicitation package. Currently the site visit is projected to be held on or about July 2026. Project Period of Performance and Magnitude: The estimated performance period is 365 calendar days, including Base + Optional CLINs from issuance of Notice to Proceed. The magnitude of construction for this project is between $500,000.00 and $1,000,000.00. System for Award Management (SAM): All contractors interested in this project and doing business with the Federal Government must be registered with the System for Award Management (SAM): https://www.sam.gov Issuance of Solicitation with Requirements Information: All responsible sources may submit a proposal, which will be considered by the agency. NOAA anticipates publishing the solicitation and supporting documents package on or about June 18, 2026, with an estimated Offer/Receipt Date/Time: July 20, 2026 at 12:00PM Eastern Time (ET) The solicitation will be available electronically at the S.A.M. website: www.sam.gov. No paper copies, faxes, or emails will be available. Any questions regarding gaining access to the materials shall be directed to Mr. Paul Tucker at paul.tucker@noaa.gov and Ms. Noelle Albert at noelle.albert@noaa.gov.

Who won similar work

10 award notices on SAM.gov in the last 24 months. Match: Same office, same NAICS 236220.

WinnerAwardsValueLast
JNB SERVICES LLC2$1.8MSep 22, 2025
PURE ENVIRO-MANAGEMENT, LLC2$981KSep 22, 2025
BALFOUR BEATTY CONSTRUCTION, LLC1$32.2MMay 27, 2026
J G M PROPERTY GROUP, INC.1$1.7MSep 18, 2026
Total Solution LLC1$230KSep 8, 2026
BHI CONSTRUCTION, LLC1$132KFeb 6, 2026
EARTHWORX EXCAVATION LLC1$54KMay 28, 2026
Uluniu Construction LLC1$11KSep 16, 2025

Value counts single-winner awards. "Shared" awards are multiple-award contracts that list every winner with the same total ceiling; that ceiling is not one company's win, so it is not added in.

Latest awards

Competitive landscape

For the 8 most frequent past winners above. Lobbying is matched by the company's exact name or exact ticker; agencies are as named on the filings.

  • 0 of these past winners lobbied Natl Oceanic & Atmospheric Administration (NOAA) since 2024 (0 filings)
  • 0 of their lobbyists list a past Natl Oceanic & Atmospheric Administration (NOAA) job
  • No corporate PAC money from them to the overseeing committees since 2024
  • 0 foreign-agent (FARA) registrations
See who and the source records with Pro

Policy around it

Bills the past winners named while lobbying this agency's issues, rules from the department, and executive orders that name the agency, last 12 months.

  • 0 bills named on the past winners' lobbying filings
  • 304 rules from the department in the last 12 months
  • 0 executive orders naming the agency in the last 12 months
See who and the source records with Pro

Market

For past winners matched exactly to a listed company. Insider trades are open-market buys and sells (Form 4) in the last 90 days, shown as facts; our own study found insiders do not reliably buy ahead of awards.

  • 0 of the past winners are listed companies
  • 0 insider buys and 0 insider sells at them in the last 90 days
See who and the source records with Pro

Sources: SAM.gov notices and award notices; Senate LDA lobbying filings; FEC filings; FARA; Federal Register; congress.gov; SEC Form 4. Every row above links to its record.

Companies are matched to tickers by exact name only. A company we could not match shows no market rows; that is a miss, not a finding.