Z1DA--632-16-101 UPGRADE EMERGENCY GENERATORS - PHASE I
Veterans Affairs · 242-NETWORK CONTRACT OFFICE 02 (36C242)
Capture briefs (a one-page, shareable copy of this page) are part of Pro. The CSV here holds the notice, its timeline and past awards.
Where this opportunity stands
Every notice posted under solicitation 36C24225R0007 in this department, oldest first.
Next steps for this stage
Standard steps for the notice type; not advice about this buyer.
- Decide bid or no bid before the response deadline.
- Look at the past winners for likely competitors and teaming partners.
- Follow the opportunity to hear about amendments and the award.
What the notice says
RFI#2 Emergency Generator Solicitation # 36C24225R007 1. Does VA fill 2-fuel storage tanks after load bank and generator test? Specification section 263213 3.2.O requires that the contractor fill the main storage tank and day tank at the completion of all field tests. This shall require all main fuel tanks to be filled at the completion of all field testing. The contractor shall also provide all fuel for testing. 2. Is Schneider electric doing refurbishment and installation of all replacement breakers in gear `room? Keynote 3 states Square D/Schneider Electric is basis of design. Schneider thr… (show all)
ough Colonial Electric has provided a scope of work and quote for a manufacturer replacement circuit breaker designed to fit within the existing switch gear this contract does not limit the manufacturer selection to Square D/Schneider Electric. 3. Are we following VA Specification for all electrical wiring installation? Contractor to following all project specifications as issued. 4. For the above-mentioned solicitation, the "wage rate sheet" attachment will not open. can you provide or post it in a different format? See attached. 5. Please confirm that CQC System Manager may have fill other roles, including project superintendent. Specification section 014500 part 3.4.B, if the Project Superintendent meets CQC System Manager qualifications and VA approval, the CQC System Manager could serve dual duties as Project Superintendent. 6. Is the GC required to use Submittal Exchange? If so, does the GC need to include the cost as part of their bid? Contractor and sub-contractors are required to utilize Autodesk Construction Cloud (ACC) for any construction related documentation exchange. Access to ACC platform is provided to contractors at no cost for the duration of the project. Refer to specification 013200 Construction Documentation included in the solicitation. 7. Is there a geotechnical report that can be provided? A Geotechnical report does not exist for this project since the government would not allow borings to be conducted during the design phase. See specification section 014529 3.1. 8. Is there an environmental (soils, other hazardous materials) report available that can be provided? See attached soil report. 9. How will unsuitable and/or contaminated soils be handled? (i.e. priced as a change order or allowance?) See specification section 312000 3.6.E. 10. Are taxes applicable on this project? Yes. 11. Per specification 01 00 00-1.3 there are 3 bid items but no location to fill in on the SF1442. Is there a pricing page missing from the SF1442? The Bid Alternate page is missing from the SF 1442. Please see attached. 12. For each bid item, please confirm that these are priced as sequential deducts and not stand alone. On sheet GI001 schedule of bid items states A: Item 1 is the projects base bid and B: Item 2 is the Bid Deduct 1 minus the items included. 13. What fire alarm system is currently in place? The current fire alarm system in place is the Edwards EST3 series. 14. What BAS system is currently in place? The current BAS is Johnson Controls FX. 15. Can AISC certification be waived on this project? The steel scope is not substantial enough for many of the certified companies in the area. AISC certification is required and cannot be waived. 16. Alternate bid items are not consistently identified throughout the plans (alternates shown on Aseries drawings but not on E-series). Please confirm that there are indeed (2) alternate bid items and clearly define the associated scopes. On sheet GI001 there is 1 deduct alternative item. E-series sheets show phasing notes on EG001, new callout added to electrical floor plan EP101, and on the electrical one-line EE602. 17. Is the contractor required to provide the initial fuel for the generator day tanks? Specification section 263213 3.2.O requires that the contractor fill the main storage tank and day tank at the completion of all field tests. This shall require all main fuel tanks to be filled at the completion of all field testing. The contractor shall also provide all fuel for testing. 18. What size are the existing domestic water and fire lines? The size of the piping is as follows: fire protection 10 in diameter and domestic water 8 in diameter. 19. The demo plans call for cutting, capping, and removing the existing water main. Will the new water main be installed before the demo? The new water main will be installed immediately after the new point of connection is established and the overburden is removed from the existing duct bank. This will be during demolition and a domestic water shutdown will require scheduling with the VA. 20. Details call for a tapping sleeve and gate valve for the water services 4" to 8". Will this be required for the domestic and fire line relocates? The connection tap, in the water services detail, is not applicable. The project does not involve the installation of a connection tap. This project only involves the relocation of the sprinkler and domestic main piping. 21. The final cut and caps of the domestic and fire line will require a shutdown. How long are we allowed to shut down the water for? Can this be done during day-time hours? Water shut down shall be done on the weekend during the minimal water usage. Work shall be prepared and phased to minimize the shutdown to no more than 8 hours.� 22. Can the Bid Date be extended another week? The RFP due WILL be extended to January 14, 2025, at 11:00 AM. 23. Will there be another one? No, only one site visit was schedule for this project. 24. I also see this is a negotiated bid. Will we be able to provide a quote that will be considered being that we did not go to the site visit? Yes, your firm can still submit an RFP regardless of if you attended the site visit or not. The site visit was not mandatory. 25. Will you be uploading a copy of the sign in sheet to SAM? (if so when do you anticipate). See attached. DRAWINGS: 1. The following drawings are revised as follows (attached): a. AE101: The concrete pad width, under NEW 200CR , is to be extended to 7-feet. b. C-0.0: Add GENERAL SHEET NOTE 1 - The existing fire protection piping, within the new building area, shall be demolished and removed. All work shall be completed during Phase 2. c. C-2.0: Add GENERAL SHEET NOTE 1 The new fire protection piping shall be installed prior to the end Phase 2. 2. Drawing sheets are reissued as follows: a. PD101: i. Partial basement plan was added illustrating the existing main water main to be demolished. ii. Supporting key notes 4, 5, and 6 have been added. b. P101: i. Partial basement plan was added illustrating the new domestic water main connection to the existing domestic water main. ii. Supporting key notes 7 and 8 have been added. c. EP101: i. Adjusted the equipment footprint of NEW 200CR, 200EQ, and 200EQ4 to accurately match the manufacturer s physical dimensions. ii. Relocated NEW 200NDP1 from A0-11B Switchgear room to A0-11 Access to Utilities Room. d. EY-101: i. Adjusted the equipment footprint of NEW 200CR, 200EQ, and 200EQ4 to accurately match the manufacturer s physical dimensions. ii. Relocated NEW 200NDP1 from A0-11B Switchgear room to A0-11 Access to Utilities Room. e. EE-404: i. Adjusted the equipment footprint of NEW 200CR, 200EQ, and 200EQ4 to accurately match the manufacturer s physical dimensions. ii. Relocated NEW 200NDP1 from A0-11B Switchgear room to A0-11 Access to Utilities Room. iii. Adjusted conduit routing to 200NDP1. f. EE602: i. Added ATS sizes to the drawings. ii. Added output feeder sizes for all ATS . iii. Added MCB to the 200LS panelboard. iv. Removed main breaker out of 200EQ4. g. EE702: i. Updated the schedule for 200CR. h. EE703 i. Updated the schedule for 200EQ. ii. Updated the schedule for 200EQ4.
Who won similar work
12 award notices on SAM.gov in the last 24 months. Matched by: Same office (242-NETWORK CONTRACT OFFICE 02 (36C242)), same product/service code (PSC) Z1DA and NAICS 236220.
Single-winner award sizes (12): middle half $822K to $6.2M, median $2.5M; range $99K to $45.6M.
| Winner | Awards | Value | Last |
|---|---|---|---|
| SERVIAM CONSTRUCTION LLC | 2 | $17.4M | Jul 11, 2025 |
| IRON SWORD ENTERPRISES, LLC | 2 | $1.7M | Mar 30, 2026 |
| Amerifield JV LLC | 1 | $45.6M | Aug 28, 2025 |
| WAINSCHAF ASSOCIATES, INC. | 1 | $13.3M | Jun 30, 2026 |
| F & C GROUP JV LLC | 1 | $3.9M | Apr 8, 2026 |
| PATRIOT SONS USA LLC | 1 | $2.5M | Jul 29, 2025 |
| TACTICAL CONSTRUCTION, INC | 1 | $2.5M | Aug 5, 2025 |
| VETERANS HOPE ASSOCIATES INC | 1 | $890K | Sep 23, 2026 |
| J & J MECHANICAL AND CONSTRUCTION GROUP LLC | 1 | $559K | Mar 25, 2025 |
| NORTHERN DREAMS CONSTRUCTION, INC | 1 | $99K | Sep 9, 2025 |
Value counts single-winner awards. "Shared" awards are multiple-award contracts that list every winner with the same total ceiling; that ceiling is not one company's win, so it is not added in. Revenue next to a ticker is the company's last annual revenue from its 10-K.
- Sep 23, 2026VETERANS HOPE ASSOCIATES INC$890KZ1DA--NRM - CONST - 630A4-26-411 CORRECT DEFICIENCY OF 14 WEST AND 15 WEST - FY27 NRMNo listed company matched (Materiality N/A)
- Jun 30, 2026WAINSCHAF ASSOCIATES, INC.$13.3MZ1DA--NRM CONSTRUCTION -528A8-18-801 Renovate for Cardiac Cath & IRNo listed company matched (Materiality N/A)
- Apr 8, 2026F & C GROUP JV LLC$3.9MZ1DA-- Replace Emergency Room AHUNo listed company matched (Materiality N/A)
- Mar 30, 2026IRON SWORD ENTERPRISES, LLC$1.1MZ1DA--Albany VAMC BMS Network ConstructionNo listed company matched (Materiality N/A)
- Sep 9, 2025NORTHERN DREAMS CONSTRUCTION, INC$99KZ1DA--528-25-116 Bldg. 1, 1st Floor, E-Wing Interior Entry Renovations (VA-25-00087336)No listed company matched (Materiality N/A)
- Aug 28, 2025Amerifield JV LLC$45.6MZ1DA--NRM-CONST Proj#632-22-900 Upgrade Boiler PlantNo listed company matched (Materiality N/A)
- Aug 5, 2025TACTICAL CONSTRUCTION, INC$2.5MZ1DA--NRM-CONST PROJ#528A5-21-504-Upgrade Fire Alarm SystemNo listed company matched (Materiality N/A)
- Jul 29, 2025PATRIOT SONS USA LLC$2.5MZ1DA--STATION-CONST VAWNYHS DEMOLITION AND ABATEMENT IDIQNo listed company matched (Materiality N/A)
- Jul 11, 2025SERVIAM CONSTRUCTION LLC$2.7MZ1DA--528A5-20-508 RENOVATE BUILDING 36No listed company matched (Materiality N/A)
- Mar 25, 2025J & J MECHANICAL AND CONSTRUCTION GROUP LLC$559KZ1DA--630-24-801 Emergency Repairs at ManhattanNo listed company matched (Materiality N/A)
Competitive landscape
For the 8 most frequent past winners above. Lobbying is matched by the company's exact name or exact ticker; agencies are as named on the filings.
- 0 of these past winners lobbied Veterans Affairs, Dept of (VA) since 2024 (0 filings)
- 0 of their lobbyists list a past Veterans Affairs, Dept of (VA) job
- No corporate PAC money from them to the overseeing committees since 2024
- 0 foreign-agent (FARA) registrations
Policy around it
Bills the past winners named while lobbying this agency's issues, rules from the department, and executive orders that name the agency, last 12 months.
- 0 bills named on the past winners' lobbying filings
- 25 rules from the department in the last 12 months
- 0 executive orders naming the agency in the last 12 months
Market
For past winners matched exactly to a listed company. Insider trades are open-market buys and sells (Form 4) in the last 90 days, shown as facts; our own study found insiders do not reliably buy ahead of awards. A sale marked 10b5-1 was made under a trading plan set up in advance.
- 0 of the past winners are listed companies
- 0 insider buys and 0 insider sells at them in the last 90 days
Sources: SAM.gov notices and award notices; Senate LDA lobbying filings; FEC filings; FARA; Federal Register; congress.gov; SEC Form 4. Every row above links to its record.
Companies are matched to tickers by exact name only. A company we could not match shows no market rows; that is a miss, not a finding.