Pre-solicitationPosted Apr 30, 2026

Construction Services for New Haven Harbor Improvement Dredging in New Haven, CT

Army Corps of Engineers · W2SD ENDIST NEW ENGLAND

Stage
Early notice (sources sought, presolicitation or special notice)
NAICS
237990
Value
Not stated
Solicitation
W912WJ26BA012
Set-aside
None stated
PSC
Y1QA
Place
New Haven, CT, USA
Contact
Kyle Hall (kyle.k.hall@usace.army.mil)
Loading your pipeline and notes…
CSV Email

Capture briefs (a one-page, shareable copy of this page) are part of Pro. The CSV here holds the notice, its timeline and past awards.

Where this opportunity stands

Every notice posted under solicitation W912WJ26BA012 in this department, oldest first.

Early notice
  • Apr 30, 2026 · this notice
    Pre-solicitation
Solicitation
  • May 19, 2026
    Solicitation
    Open
  • Jun 4, 2026
    Solicitation
    Open
  • Jun 11, 2026
    Solicitation
    Open
  • Jun 25, 2026
    Solicitation
    Open
  • Jul 6, 2026
    Solicitation
    Open
  • Jul 8, 2026
    Solicitation
    Open
  • Jul 14, 2026
    Solicitation
    Open
  • Jul 16, 2026
    Solicitation
    Open
  • Jul 20, 2026
    Solicitation
    Open
  • Jul 20, 2026
    Solicitation
    Open
  • Sep 15, 2026
    Solicitation
    Open
Award
Not yet. Typical award: Jul 22, 2026 to Sep 18, 2026, middle of the range Aug 21, 2026.
Measured from 64 past early notices at Dept of the Army with NAICS 237990 that later posted an award (middle half of cases, counted from Apr 30, 2026).

Next steps for this stage

Standard steps for the notice type; not advice about this buyer.

  • Answer the notice: this is when the requirement can still be shaped.
  • Contact the contracting officer named on the notice.
  • Check who won similar work; they are the likely bidders.

What the notice says

The U.S. Army Corps of Engineers, New England District will be issuing an Invitation for Bids for Improvement Dredging of the New Haven Harbor Federal Navigation Project (FNP) located in New Haven, CT. This procurement is an Unrestricted Invitation for Bid (IFB). The NAICS code for the work is 237990, Other Heavy and Civil Engineering Construction, with a size standard of $37M. Construction is expected to take about nineteen months to complete. The estimated construction cost is between $50,000,000.00 and $100,000,000.00. Any responsible contractor meeting this standard may submit a bid to be … (show all)

considered by the New England District. The New Haven Harbor Improvement Dredging project consists of mechanically dredging the navigation channel and turning basin from the current 35-foot depth and channel limits to the newly authorized 40-foot depth below mean lower low water (MLLW). The New Haven Harbor FNP extends from Long Island Sound to the confluence at the Quinnipiac River. In addition to deepening, the project expands channel limits: the entrance channel will widen to 600 feet, the bend through the breakwaters to 800 feet, and the main channel between the breakwaters and terminals to 500 feet. This improvement effort involves the removal of up to 3,500,000 CY of fine-grained silt and organic material, 850,000 cubic yards (CY) of medium-to-fine grained sand material, and 60,000 CY of rock. It is expected that some areas of rock may require blasting or other pre-treatment methods. Rock in the channel is to be removed down to a minimum elevation -42 Feet MLLW with a 2-foot allowable overdepth. All other areas are required to be dredged to -40 Feet MLLW with a 2-foot allowable overdepth. Mechanically dredged material will be placed into scows for transport and disposal, which is split between four local disposal sites and one open ocean disposal site. Central Long Island Sound Disposal Site (CLDS), approximately 7 miles south of the FNP, is the primary material placement site for the project. Four additional placement sites within the harbor and generally within 1 nautical mile of the channel will receive up to 1,500,000 CY of material for beneficial use. Access to these beneficial use sites may require transfer of scows in water depths as shallow as 10 Feet � 15 Feet MLLW (New Haven, CT mean tide range ~ 6ft). Dredging and disposal operations are anticipated to take roughly 9 to 10 months over two dredging seasons and will be performed during Season One between 1 October 2026 to 1 March 2027 and the Season Two period from 1 October 2027 to 1 March 2028 to meet environmental time of year (ToY) restrictions. In order to accomplish all dredging requirements within the specified dredging windows it is expected that the Contractor will need to meet a minimum production rate of 300,000 CY per 30 consecutive calendar days. Environmental coordination and permitting has been completed by the U.S. Army of Engineers, New England District. This is not an invitation for bids at this time. The solicitation requirements and contract documents including instructions for submission and the response date will be available on or about May 18, 2026. Neither telephonic, mailed, nor faxed requests for hard copies of this solicitation will be accepted. The solicitation will only be available online; in order to download the solicitation, offerors must access the System of Award Management website (https://sam.gov/). All responsible sources may submit a bid which shall be considered by the New England District. Additional questions may be emailed to Kyle Hall, New England District Contract Specialist, at kyle.k.hall@usace.army.mil or by phone at (978) 318-8479.

Who won similar work

6 award notices on SAM.gov in the last 24 months. Matched by: Same office (W2SD ENDIST NEW ENGLAND), same product/service code (PSC) Y1QA and NAICS 237990.

Single-winner award sizes (6): middle half $1.4M to $8.7M, median $2.5M; range $1.1M to $69.5M.

WinnerAwardsValueLast
GREAT LAKES DREDGE & DOCK CO, LLC1$69.5MSep 15, 2026
AGATE CONSTRUCTION COMPANY1$10.6MFeb 25, 2026
MANSON CONSTRUCTION CO Seattle WA 98134 USA1$2.9MSep 9, 2026
AGM MARINE CONTRACTORS INC1$2.1MFeb 6, 2026
PONTIAC DRYWALL SYSTEMS INC.1$1.2MJul 11, 2025
BUILDING INNOVATORS LLC1$1.1MFeb 15, 2025

Value counts single-winner awards. "Shared" awards are multiple-award contracts that list every winner with the same total ceiling; that ceiling is not one company's win, so it is not added in. Revenue next to a ticker is the company's last annual revenue from its 10-K.

Latest awards

Competitive landscape

For the 6 most frequent past winners above. Lobbying is matched by the company's exact name or exact ticker; agencies are as named on the filings.

  • 0 of these past winners lobbied Army, Dept of (Corps of Engineers) or Army, Dept of (Other) or Natl Guard since 2024 (0 filings)
  • 0 of their lobbyists list a past Army, Dept of (Corps of Engineers) or Army, Dept of (Other) or Natl Guard job
  • No corporate PAC money from them to the overseeing committees since 2024
  • 0 foreign-agent (FARA) registrations
See who and the source records with Pro

Policy around it

Bills the past winners named while lobbying this agency's issues, rules from the department, and executive orders that name the agency, last 12 months.

  • 0 bills named on the past winners' lobbying filings
  • 32 rules from the department in the last 12 months
  • 0 executive orders naming the agency in the last 12 months
See who and the source records with Pro

Market

For past winners matched exactly to a listed company. Insider trades are open-market buys and sells (Form 4) in the last 90 days, shown as facts; our own study found insiders do not reliably buy ahead of awards. A sale marked 10b5-1 was made under a trading plan set up in advance.

  • 0 of the past winners are listed companies
  • 0 insider buys and 0 insider sells at them in the last 90 days
See who and the source records with Pro

Sources: SAM.gov notices and award notices; Senate LDA lobbying filings; FEC filings; FARA; Federal Register; congress.gov; SEC Form 4. Every row above links to its record.

Companies are matched to tickers by exact name only. A company we could not match shows no market rows; that is a miss, not a finding.