Special NoticePosted Jul 21, 2026·Responses due Jul 27, 2026

ADVANCE NOTICE TO INDUSTRY: UPCOMING PROGRESSIVE DESIGN-BUILD OTHER TRANSACTION PROCUREMENT

Army Corps of Engineers · W074 ENDIST SAVANNAH

Stage
Early notice (sources sought, presolicitation or special notice)
NAICS
236220
Value
Not stated
Solicitation
None
Set-aside
No Set aside used
PSC
Y1FC
Place
Fort Stewart, GA, USA
Contact
Jason Scheil (jeremiah.j.scheil@usace.army.mil)
Loading your pipeline and notes…
CSV Email

Capture briefs (a one-page, shareable copy of this page) are part of Pro. The CSV here holds the notice, its timeline and past awards.

Where this opportunity stands

This notice has no solicitation number, so earlier and later notices cannot be tied to it.

Early notice
  • Jul 21, 2026 · this notice
    Special Notice
Solicitation
None posted
Award
Not yet. Typical award: Nov 10, 2026 to Apr 2, 2027, middle of the range Dec 15, 2026.
Measured from 62 past early notices at Dept of the Army with NAICS 236220 that later posted an award (middle half of cases, counted from Jul 21, 2026).

Next steps for this stage

Standard steps for the notice type; not advice about this buyer.

  • Answer the notice: this is when the requirement can still be shaped.
  • Contact the contracting officer named on the notice.
  • Check who won similar work; they are the likely bidders.

What the notice says

ADVANCE NOTICE TO INDUSTRY: UPCOMING PROGRESSIVE DESIGN-BUILD OTHER TRANSACTION PROCUREMENT W912HH-26-9-0001 Fort Stewart Building 212 UEPH Barracks Repair by Replacement Pilot Program U.S. Army Corps of Engineers (USACE) � Savannah District Anticipated Release Date: July 28, 2026 Project: PN 111716 Bldg 212 Repair by Replacement, Fort Stewart, Georgia Statutory Authority: 10 U.S.C. � 2808a (Other Transaction Authority for Facility Construction and Repair) NAICS Code: 236220 (Commercial and Institutional Building Construction) PSC Code: Y1FC (CONSTRUCTION OF TROOP HOUSING FACILITIES) Anticipat… (show all)

ed Maximum Value (NTE): $38,000,000 NOTICE PURPOSE & PLANNING CONTEXT The U.S. Army Corps of Engineers (USACE), Savannah District, is issuing this Advance Notice to alert the construction industry, industrialized manufacturers, and modular integrators to an upcoming design-build opportunity. This project will be executed as an Other Transaction Agreement (OTA) under the statutory authority of 10 U.S.C. � 2808a, Facility Construction or Repair. This is NOT a formal solicitation. This notice is for planning purposes only and is non-committal. The official Request for Qualifications (RFQ) / Request for White Papers is anticipated for release on SAM.gov in late July 2026. PROJECT SCOPE This project consists of the design and construction of a new 86-bed Permanent Party Unaccompanied Enlisted Personnel Housing (UEPH) Barracks and the demolition of the existing building 212 at Fort Stewart, GA, after the new barracks has been turned over and completed. The scope includes parallel site preparation, utility infrastructure, factory-based manufacturing, and the procurement and installation of all necessary furniture, furnishings, and equipment (FF&E). The new facility will have a maximum gross area of 41,710 square feet (485 sq ft per occupant) and is intended to provide housing that is functionally and technically comparable to similar private-sector housing. Barracks functional spaces will adhere to the 2025 Army Barracks Standard for Permanent Party Unaccompanied Housing, Junior Enlisted and Junior NCOs Memorandum for square footages, with the exception of the required room module layout. ANTICIPATED TWO-STEP SELECTION PROCESS USACE Savannah District intends to utilize a streamlined, two-step qualifications-based selection (QBS) process to identify the most qualified partner. The information below could change before the final release of the request for white papers. STEP 1: REQUEST FOR QUALIFICATIONS (RFQ) / WHITE PAPERS Interested firms will submit a concise written qualifications package (maximum of 15 pages). Submissions will be evaluated against two main elements: Capability and Experience Relevant Experience: Demonstration of more than two (2) new construction projects of similar size (minimum 30,000 SF) and scope (multi-unit housing, dormitories, barracks). Renovations are not accepted as comparable. Innovation & Speed: Documented use of innovative, accelerated, or off-site delivery techniques that successfully compressed schedule and cost. Technical and Management Approach Understanding: Demonstrated understanding of the project goals, constraints and affordability to stay within the budget ceiling. Design Management: Approach to managing the design process, ensuring compliance with the 2025 Army Barracks Standard, UFCs, and standard building codes. Manufacturing Experience: Explain the current manufacturing process and output and how that would relate and support this project. Collaborative DB Philosophy: The firm�s management philosophy regarding Collaborative DB, focusing on partnership and transparent costing. Organizational Structure: Clarity and effectiveness of the proposed Organizational Chart identifying key roles and reporting lines. The Government will shortlist and invite up to three (3) of the most highly qualified firms to Step 2. STEP 2: PITCH MEETINGS & FACILITY TOURS The Step 2 evaluation moves away from written proposals to assess physical plant readiness and live team dynamics: Interactive Pitch Meetings: Shortlisted firms will participate in a confidential, collaborative working session with the USACE Project Delivery Team to evaluate: Collaborative Capability & Risk Management (Pitch Presentation): Joint scope validation, real-time technical problem-solving, team chemistry. Facility Site Visits: The Evaluation Team will tour the shortlisted firms' proposed manufacturing plants to verify production capacity and plant readiness. TENTATIVE PROCUREMENT SCHEDULE The Savannah District is executing this acquisition on an aggressive timeline to meet critical end-of-fiscal-year deadlines: Milestone Event Target Date Release of Request for White Papers (RFQ)- July 28, 2026 Step 1 Submissions (White Papers) Due- August 6, 2026 Notification of Step 1 Shortlist- August 18, 2026 Step 2 Factory Site Visits / Tours and Pitch Presentations- August 19 � September 2, 2026 Selection of Most Highly Qualified Partner- September 8, 2026 Initiate Phase 1 Agreement & Terms Negotiations- September 9 OT Agreement Award (Full NTE Obligation)- September 30, 2026 Inquiries & SAM.GOV TRACKING All preliminary general inquiries, clarification requests, and communications regarding this advance notice must be submitted via ProjNet: https://www.projnet.org/projnet Bidder Inquiry Key: UTKUDU-RCT6X2 All future procurement files, notices, and the final RFQ solicitation package will be posted to the System for Award Management (SAM.gov) and the PIEE Solicitation Module. Interested parties are solely responsible for monitoring SAM.gov for official releases and updates. OFFICIAL DISCLAIMER This advance notice does not constitute a Request for Proposals (RFP), a Request for White Papers, or a promise by the Government to issue a solicitation in the future. The Government is not seeking proposals or bids at this time. USACE is not responsible for any administrative, travel, engineering, or proposal costs incurred by industry in response to this notice or in preparation for Step 1 submissions.

Who won similar work

21 award notices on SAM.gov in the last 24 months. Matched by: Same office (W074 ENDIST SAVANNAH), same NAICS 236220.

Single-winner award sizes (13): middle half $23.7M to $99.0M, median $45.3M; range $9.4M to $165.9M.

WinnerAwardsValueLast
ACC CONSTRUCTION CO, INC2$275.7MAug 1, 2025
TREND CONSTRUCTION INC2$118.6MJun 12, 2025
BL HARBERT INTERNATIONAL LLC1$124.8MMar 31, 2026
C & C CONTRACTORS LLC1$99.0MDec 3, 2024
V LINE SERVICES L.L.C.1$45.4MJan 26, 2026
COPPER CONSTRUCTION COMPANY1$45.3MAug 25, 2025
BUILDZ, LLC1$38.0MOct 1, 2026
GLOBAL GO, LLC1$37.9MSep 9, 2026
COOPER TACIA GENERAL CONTRACTING COMPANY1$23.7MJun 12, 2025
JNB Services, LLC1$14.5MJul 6, 2026

Value counts single-winner awards. "Shared" awards are multiple-award contracts that list every winner with the same total ceiling; that ceiling is not one company's win, so it is not added in. Revenue next to a ticker is the company's last annual revenue from its 10-K.

Latest awards

Competitive landscape

For the 8 most frequent past winners above. Lobbying is matched by the company's exact name or exact ticker; agencies are as named on the filings.

  • 0 of these past winners lobbied Army, Dept of (Corps of Engineers) or Army, Dept of (Other) or Natl Guard since 2024 (0 filings)
  • 0 of their lobbyists list a past Army, Dept of (Corps of Engineers) or Army, Dept of (Other) or Natl Guard job
  • No corporate PAC money from them to the overseeing committees since 2024
  • 0 foreign-agent (FARA) registrations
See who and the source records with Pro

Policy around it

Bills the past winners named while lobbying this agency's issues, rules from the department, and executive orders that name the agency, last 12 months.

  • 0 bills named on the past winners' lobbying filings
  • 32 rules from the department in the last 12 months
  • 0 executive orders naming the agency in the last 12 months
See who and the source records with Pro

Market

For past winners matched exactly to a listed company. Insider trades are open-market buys and sells (Form 4) in the last 90 days, shown as facts; our own study found insiders do not reliably buy ahead of awards. A sale marked 10b5-1 was made under a trading plan set up in advance.

  • 0 of the past winners are listed companies
  • 0 insider buys and 0 insider sells at them in the last 90 days
See who and the source records with Pro

Sources: SAM.gov notices and award notices; Senate LDA lobbying filings; FEC filings; FARA; Federal Register; congress.gov; SEC Form 4. Every row above links to its record.

Companies are matched to tickers by exact name only. A company we could not match shows no market rows; that is a miss, not a finding.