SolicitationPosted Mar 6, 2025·Responses due Mar 12, 2025

Spillway Dam Gallery Paint Removal, Buffumville Lake, Charlton, MA

Army Corps of Engineers · W2SD ENDIST NEW ENGLAND

Stage
Open solicitation
NAICS
238320
Value
Not stated
Solicitation
W912WJ25Q0038
Set-aside
Small Business Set Aside - Total
PSC
Y1QA
Place
Not stated
Contact
Jennifer M. Samela (jennifer.m.samela@usace.army.mil)
Loading your pipeline and notes…
CSV Email

Capture briefs (a one-page, shareable copy of this page) are part of Pro. The CSV here holds the notice, its timeline and past awards.

Where this opportunity stands

Every notice posted under solicitation W912WJ25Q0038 in this department, oldest first.

Early notice
  • Jan 31, 2025
    Pre-solicitation
    Open
Solicitation
  • Feb 20, 2025
    Solicitation
    Open
  • Feb 20, 2025
    Solicitation
    Open
  • Feb 26, 2025
    Solicitation
    Open
  • Feb 28, 2025
    Solicitation
    Open
  • Mar 6, 2025 · this notice
    Solicitation
  • Mar 10, 2025
    Solicitation
    Open
Award
  • Apr 7, 2025
    Award Notice
    Stacie Lynn Bassett Ashburnham MA 01430 USA · $162K
    Open

Next steps for this stage

Standard steps for the notice type; not advice about this buyer.

  • Decide bid or no bid before the response deadline.
  • Look at the past winners for likely competitors and teaming partners.
  • Follow the opportunity to hear about amendments and the award.

What the notice says

THE WORK CONSISTS OF: The general description below is given to indicate the approximate scope of this project only. It does not limit the work required under this Scope of Work. In general, the Base Scope of the project is to remove paint from all surfaces of concrete inside the Access and Operating Galleries. Remove all paintings/coatings down to bare concrete at North Access and Operating Galleries floor, walls and ceilings. Exception: Operating Gallery wall recess containing Operation panels and controls. Pressure inject and seal one actively leaking wall crack at South Access Gallery. Not… (show all)

e: Concrete surfaces in South Gallery is currently not painted, thus excluded from paint removal and sealer/hardener work. After paint removal, clean all previously painted surfaces of dirt, debris, and other deleterious substances, then apply two coats of penetrating sealer/hardener to stabilize and minimize future dusting. Metal surfaces embedded or part of the affected surfaces may contain a reportable level of lead compound. These surfaces shall receive surface preparation as called out in Technical Specification 09 97 02 then coated with epoxy primer/sealer and overcoat with color matching previously painted colors. Note: Floor drain grate and frame at South Access Gallery shall also be cleaned and recoated.2. Optional scope of the project is removal of paint on all concrete surfaces (ceiling, walls and floor) located at the Lower Basement of the Control House (El 500.08). Overall, condition of the painted surfaces varies from fair/good, well adhered to surface, to poor showing various degree of peeling or missing altogether. Surfaces were painted pre-1994. While paint material is unknown at this time, it has been tested and found to be lead free, except on metal handrail showing a reportable level of lead. Proper disposal of lead containing debris shall be exercised. See testing results dated April 2024 in APPENDIX D. Graphical representation of the work area is shown in APPENDIX A. Contractor access and staging area as shown in APPENDIX B. Representative As-Built drawings for the structure are shown in APPENDIX C. Additional As-Built drawings are available upon request. Prior to commencement of any removal or cleaning work, all dam operation equipment, controls and accessories shall be securely protected to preclude any dust and debris from the construction. Mask all items that will not be painted to protect them from construction work. Paint removal means and methods shall be selected by the Contractor that will best remove the existing paint from the concrete surfaces and will not damage the existing concrete surfaces. Removal approach shall be presented in sufficient detail in the Work Plan to allow review and approval by the Government. Any damages to existing concrete while performing the work shall be repaired by the Contractor. Submit repair approach and materials to the Government for review and approval. All non-concrete surfaces called out to be repainted shall receive surface preparation for repainting. Mask all adjacent areas from repainting operation. Apply sealer and overcoat with color matching existing paint color(s) that have been removed. Active work area shall have proper containment to preclude construction dust and debris from migrating into other areas of the structure. Provide adequate means of air borne dust removal including supplemental ventilation within the work area for worker protection. Dust removal means shall contain adequate filtration to preclude discharge of dust laden air into the environment. All drains within the work area shall be securely blocked during work to preclude construction debris from entering the drains. As noted above, these drains directly discharge into the stream below the dam. All solid and sludge debris from construction shall be properly removed from the work area and legally disposed offsite. Crack repair: Actively leaking crack located in the West wall of the South Access Gallery shall be repaired by pressure injection to stop the leak. Clean all surfaces from efflorescence built up and other deleterious matters. Drill and install sufficient amount of pressure injection ports either side of the crack. Pressure inject epoxy in accordance with the manufacturer�s recommendations. Repeat process as necessary for proper seal. Upon confirmation that all leaks have been arrested, remove all injection ports and plug holes with grout closely matching in color with wall surface. Scrape all excess grout/epoxy and sand smooth surfaces around work area to a smooth and neat appearance. Clean all concrete surfaces by low pressure wash or other means in preparation of application of penetrating sealer/hardener. Dry surfaces, with supplemental heat as necessary, until maximum moisture content as recommended by sealer/hardener manufacturer have been achieved and validated by testing. Apply two coats of sealer/hardener in uniform fashion following manufacturer�s recommendation on lapse time between applications. Note: Concrete surfaces at South Gallery shall be cleaned only. Application of penetrating sealer/hardener is not required at this Gallery. Restore all areas affected by construction to a clean and sound operating condition. All masking, covering and debris shall be removed and properly disposed of. The magnitude of construction is between $100,000 and $250,000. For additional information on construction contracts awarded to small businesses please visit: Partnering With Us (army.mil). This procurement is set-aside for small business vendors. The applicable NAICS code is 238320 with a Small Business Size Standard of $19 Million. ALL VENDORS MUST HAVE AN ACTIVE REGISTRATION IN SAM.GOV AT THE TIME OF SUBMISSION IN ORDER TO BE CONSIDERED. ANY VENDOR THAT DOES NOT HAVE AN ACTIVE SAM.GOV REGISTRATION WILL BE REJECTED AS NON RESPONSIVE.

Who won similar work

6 award notices on SAM.gov in the last 24 months. Matched by: Same office (W2SD ENDIST NEW ENGLAND), same product/service code (PSC) Y1QA and NAICS 238320.

Single-winner award sizes (6): middle half $87K to $302K, median $187K; range $35K to $1.2M.

WinnerAwardsValueLast
ENVIROLOGICS INC2$1.5MSep 26, 2025
QUODDY BUILDERS LLC1$277KJul 22, 2026
TBG EE JV II, LLC1$98KSep 18, 2025
SCHOLAR PAINTING, LLC1$83KMay 19, 2025
KOMMODITIES CORP1$35KSep 25, 2026

Value counts single-winner awards. "Shared" awards are multiple-award contracts that list every winner with the same total ceiling; that ceiling is not one company's win, so it is not added in. Revenue next to a ticker is the company's last annual revenue from its 10-K.

Latest awards

Competitive landscape

For the 5 most frequent past winners above. Lobbying is matched by the company's exact name or exact ticker; agencies are as named on the filings.

  • 0 of these past winners lobbied Army, Dept of (Corps of Engineers) or Army, Dept of (Other) or Natl Guard since 2024 (0 filings)
  • 0 of their lobbyists list a past Army, Dept of (Corps of Engineers) or Army, Dept of (Other) or Natl Guard job
  • No corporate PAC money from them to the overseeing committees since 2024
  • 0 foreign-agent (FARA) registrations
See who and the source records with Pro

Policy around it

Bills the past winners named while lobbying this agency's issues, rules from the department, and executive orders that name the agency, last 12 months.

  • 0 bills named on the past winners' lobbying filings
  • 32 rules from the department in the last 12 months
  • 0 executive orders naming the agency in the last 12 months
See who and the source records with Pro

Market

For past winners matched exactly to a listed company. Insider trades are open-market buys and sells (Form 4) in the last 90 days, shown as facts; our own study found insiders do not reliably buy ahead of awards. A sale marked 10b5-1 was made under a trading plan set up in advance.

  • 0 of the past winners are listed companies
  • 0 insider buys and 0 insider sells at them in the last 90 days
See who and the source records with Pro

Sources: SAM.gov notices and award notices; Senate LDA lobbying filings; FEC filings; FARA; Federal Register; congress.gov; SEC Form 4. Every row above links to its record.

Companies are matched to tickers by exact name only. A company we could not match shows no market rows; that is a miss, not a finding.