CJAG Fence Install
Army · W7NU USPFO ACTIVITY OH ARNG
Capture briefs (a one-page, shareable copy of this page) are part of Pro. The CSV here holds the notice, its timeline and past awards.
Where this opportunity stands
Every notice posted under solicitation W9136426P0000040380 in this department, oldest first.
Next steps for this stage
Standard steps for the notice type; not advice about this buyer.
- Decide bid or no bid before the response deadline.
- Look at the past winners for likely competitors and teaming partners.
- Follow the opportunity to hear about amendments and the award.
What the notice says
Amendment 1 � Q&A � 16 Sep 26 Question1. The PWS references two 20-foot manual sliding security gates and also states that two 20-foot manual gate openings are to be installed. Please confirm whether the requirement is for two separate 20-foot manual sliding gate openings, or one 40-foot opening consisting of two 20-foot sliding gate leaves that close together. Answer 1: The requirement is for two separate 20-foot manual sliding gates. Question 2. Gate Configuration: PWS Paragraph 5.1 identifies two 20-foot manual sliding security gates, while Paragraph 5.1.5 references �swing clearance.� Plea… (show all)
se confirm whether the required gates are manual sliding gates, swing gates, or another configuration. Answer 2: The requirement is for two separate 20-foot manual sliding gates. Question 3. Field Measurements / Site Access: The PWS requires the contractor to verify all measurements prior to submitting a quotation. Will the Government conduct a scheduled site visit or otherwise provide access to Load Line 6 for prospective contractors to perform the required field verification before the quotation due date? Answer 3: Site visits can be scheduled by contacting CW2 Grant Stoner (614-336-6580, grant.m.stoner.mil@army.mil) or MAJ Kyle Miller (kyle.r.miller56.mil@army.mil). Question 4. Fence Alignment / Drawings: Are drawings, site plans, maps, or other documents available identifying the exact proposed fence alignment and locations of the two 20-foot gates? Answer 4: Yes, drawing is attached and ARNG will perform layout prior to fencing installation after the vegetation clearing is complete. Question 5. Completion Schedule: The PWS states a six-month period of performance from contract award; however, the solicitation instructions require a proposed schedule demonstrating completion prior to December 1, 2026. Please confirm whether December 1, 2026 is the mandatory completion deadline or whether the contractor will receive six months from the date of award. Answer 5: The contractor will receive a six-month period to complete the work, but the work should be scheduled immediately upon award of the contract, and if possible, the government would like completion prior to 1 December. Question 6. Underground Utilities: The PWS directs the contractor to coordinate with CJAG Department of Public Works to locate and mark underground utilities. Will CJAG/DPW perform the utility locating and marking at no cost to the contractor, or should the contractor include any associated utility-locate costs in its quotation? Answer 6: There are no live underground utilities in the area. Question 7. Permits: Are any local, state, installation, excavation, or construction permits required for this project? If so, please identify which permits the contractor is responsible for obtaining and paying for. Answer 7: The contractor must comply with the Ohio National Guard Environmental requirements, but no additional permits are required for this project. Question 8. Site Conditions / Clearing: Can the Government provide additional information or photographs showing the existing conditions along the approximately 3,850-linear-foot fence alignment, particularly the amount of brush, vegetation, grading, or other site preparation anticipated within the required 10-foot-wide clearing corridor? Answer 8: Fence line installation will be cleared to a minimum of 30 feet left and right of center via another project prior to fence installation. The area will be graded so that grass is planted and mowing can be accomplished. Question 9. Excess Soil / Disposal: May excess soil generated from the post-hole excavation be spread or relocated on Government property at a location designated by the COR, or must all excess soil be removed from Camp James A. Garfield and disposed of off-site? Answer 9: A minimum amount of excess soil may remain on the site if it can be spread to conform to the natural grade on the site. Question 10. Installation Access: Is there an anticipated processing timeframe for contractor and subcontractor personnel to obtain installation access/background-check approval? Additionally, are there any vehicle, equipment, escort, or badging requirements bidders should account for when developing their pricing and schedule? Answer 10: All access requirements are provided in the post award kick off meeting. There are no fees and no badging requirements. Question 11. Wage Requirements: Please confirm whether a Davis-Bacon Act wage determination or any other prevailing-wage requirement applies to this construction requirement. If applicable, please provide or identify the applicable wage determination. Answer 11: Wage determination for Ohio Heavy and highway applies and will be updated prior to award if a new version is available. OH20260001 07/30/2026 Question 12. Gate Hardware: Please confirm whether there are any specific requirements for gate latches, locking hardware, rollers/tracks, stops, drop rods, or other gate hardware beyond the requirements currently contained in the PWS and applicable UFS/UFC criteria. Answer 12: There are no additional requirements that are not in the PWS or applicable UFS criteria. Question 13. Government-Furnished Information: Are there any additional drawings, specifications, site photographs, utility information, or technical documents that will be provided by amendment before quotations are due? Answer 13: 01_sheets-fence-v3_redacted is the only drawing included. Request a site visit if additional information is required. ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ Amendment 1 - 10 Sep 2026 - Add POC for site visit, Added drawing, Added Q&A. Site Visits Encouraged - Call to schedule - Call 1SG Brian Persing 614-336-6975 or CW2 Grant Stoner 614-336-6580. Attachment added: 01_SHEETS-FENCE-V3.pdf Q&A Question 1. Gate Configuration: PWS Paragraph 5.1 identifies two 20-foot manual sliding security gates, while Paragraph 5.1.5 references �swing clearance.� Please confirm whether the required gates are manual sliding gates, swing gates, or another configuration. Answer 1. Manual sliding gates Question 2. Field Measurements / Site Access: The PWS requires the contractor to verify all measurements prior to submitting a quotation. Will the Government conduct a scheduled site visit or otherwise provide access to Load Line 6 for prospective contractors to perform the required field verification before the quotation due date? Answer 2. Can either have a scheduled site visit day or be available when needed by appointment with prospective contactors, although until clearing is complete not much to see. Question 3. Fence Alignment / Drawings: Are drawings, site plans, maps, or other documents available identifying the exact proposed fence alignment and locations of the two 20-foot gates? Answer 3. Fence Alignment drawing was provided (also see attached here, once clearing is complete, BDE 12T assets will be used to layout alignment. Question 4. Completion Schedule: The PWS states a six-month period of performance from contract award; however, the solicitation instructions require a proposed schedule demonstrating completion prior to December 1, 2026. Please confirm whether December 1, 2026 is the mandatory completion deadline or whether the contractor will receive six months from the date of award. Answer 4. Complete prior to December 1 is preferred, also cant start until after clearing is complete in late September / October Question 5. Underground Utilities: The PWS directs the contractor to coordinate with CJAG Department of Public Works to locate and mark underground utilities. Will CJAG/DPW perform the utility locating and marking at no cost to the contractor, or should the contractor include any associated utility-locate costs in its quotation? Answer 5. no active utilities in the area Question 6. Permits: Are any local, state, installation, excavation, or construction permits required for this project? If so, please identify which permits the contractor is responsibl
Who won similar work
3 award notices on SAM.gov in the last 24 months. Matched by: Same office (W7NU USPFO ACTIVITY OH ARNG), same product/service code (PSC) Y1PZ.
Single-winner award sizes (3): middle half $259K to $432K, median $349K; range $168K to $515K.
| Winner | Awards | Value | Last |
|---|---|---|---|
| HOVIS CONSTRUCTION LLC | 1 | $515K | Sep 30, 2026 |
| B & J ELECTRIC OF POLAND, INC. | 1 | $349K | Sep 29, 2026 |
| VASTGLOBE LOGISTICS LLC | 1 | $168K | Sep 29, 2026 |
Value counts new single-winner awards. "Shared" awards are multiple-award contracts that list every winner with the same total ceiling (same contract, or the same office, day and amount); that ceiling is not one company's win, so it is not added in. Contract modifications are not new awards and are not added in either. Notices whose amount is a placeholder such as $999,999,999 are not added in. Revenue next to a ticker is the company's revenue over the latest 12 months in its SEC filings.
- Sep 30, 2026HOVIS CONSTRUCTION LLC$515KCJAG Underground Utilities ConstructionNo listed company matched (Materiality N/A)
- Sep 29, 2026VASTGLOBE LOGISTICS LLC$168KCJAG Fence InstallNo listed company matched (Materiality N/A)
- Sep 29, 2026B & J ELECTRIC OF POLAND, INC.$349KCJAG Power DistributionNo listed company matched (Materiality N/A)
Competitive landscape
For the 3 most frequent past winners above. Lobbying is matched by the company's exact name or exact ticker; agencies are as named on the filings.
- 0 of these past winners lobbied Army, Dept of (Corps of Engineers) or Army, Dept of (Other) or Natl Guard since 2024 (0 filings)
- 0 of their lobbyists list a past Army, Dept of (Corps of Engineers) or Army, Dept of (Other) or Natl Guard job
- No corporate PAC money from them to the overseeing committees since 2024
- 0 foreign-agent (FARA) registrations
Policy around it
Bills the past winners named while lobbying this agency's issues, rules from the department, and executive orders that name the agency, last 12 months.
- 0 bills named on the past winners' lobbying filings
- 32 rules from the department in the last 12 months
- 0 executive orders naming the agency in the last 12 months
Market
For past winners matched exactly to a listed company. Insider trades are open-market buys and sells (Form 4) in the last 90 days, shown as facts; our own study found insiders do not reliably buy ahead of awards. A sale marked 10b5-1 was made under a trading plan set up in advance.
- 0 of the past winners are listed companies
- 0 insider buys and 0 insider sells at them in the last 90 days
Sources: SAM.gov notices and award notices; Senate LDA lobbying filings; FEC filings; FARA; Federal Register; congress.gov; SEC Form 4. Every row above links to its record.
Companies are matched to tickers by exact name, including the subsidiaries a company lists in its SEC filings. A company we could not match shows no market rows; that is a miss, not a finding.