SolicitationPosted Apr 16, 2026·Original deadline passed (May 14). See latest amendment for current deadline.

Y1DA--NRM-CONST 630A4-17-433 Replace Boiler Plant Main Electrical Switchgear

Veterans Affairs · 242-NETWORK CONTRACT OFFICE 02 (36C242)

In plain words

Veterans Affairs wants bids for "NRM-CONST 630A4-17-433 Replace Boiler Plant Main Electrical Switchgear". The original due date (May 14, 2026) has passed; check the latest amendment for the current one. In the last 2 years, similar work went to 10 or more companies, usually for about $760K per award. An award could come any day: the usual time to award has passed.

Put together from the facts on this page; the details and sources are below.

Stage
Open solicitation
NAICS
238210
Value
Not stated
Solicitation
36C24226B0042
Set-aside
None stated
PSC
Y1DA
Place
Not stated
Contact
Kimberly A Gomez (Contractor) (Kimberly.Gomez@va.gov)
Loading your pipeline and notes…
CSV Email

Capture briefs (a one-page, shareable copy of this page) are part of Pro. The CSV here holds the notice, its timeline and past awards.

Where this opportunity stands

Every notice posted under solicitation 36C24226B0042 in this department, oldest first.

Early notice
  • Mar 6, 2026
    Pre-solicitation
    View
Solicitation
  • Apr 16, 2026 · this notice
    Solicitation
  • May 13, 2026
    Solicitation
    View
  • May 19, 2026
    Solicitation
    View
  • May 21, 2026
    Solicitation
    View
Award
  • Oct 23, 2026
    Award Notice
    F & C GROUP JV LLC · $2.2M
    View

Next steps for this stage

Standard steps for the notice type; not advice about this buyer.

  • Decide bid or no bid before the response deadline.
  • Look at the past winners for likely competitors and teaming partners.
  • Follow the opportunity to hear about amendments and the award.

What the notice says

Project Number: 630A4-17-433 Project Title: Replace Boiler Plant Main Electrical Switchgear Scope of work Completion time: Seven Hundred thirty (730) Calendar Days Disclosure of the magnitude of construction: � Between $1,000,000 and $5,000,000. Description of Work: The general contractor (GC) shall follow Architect/Engineer 100% Issue for Construction (IFC) documents to construct and Replace Boiler Plant Main Electrical Switchgear construction project at the VA New York Harbor Healthcare System- St Albans Campus. This work shall include all necessary labor, materials, equipment, and supervisi… (show all)

on but not limited to: The project involves the replacement of the main electrical switchgear and transformers, cables, conduits, and associated appurtenances in the Boiler Plant in Building #64 (Boiler Plant). The scope of work is the design of the replacement of Substations #1 and #2, Motor Control Centers #1 and #2, and Transformers A and B. See SOW breakdown by trades as follows. The Architectural work includes support in building areas affected by the replacement of the main switchgear, which will include firestopping, miscellaneous patching and repair of wall, floor and ceiling finishes and surfaces associated with the proposed electrical work. The mechanical work includes removing the existing ventilation system and providing a new adequate ventilation system and cooling upgrades to accommodate heat loads generated by new electrical room gear to comply with the VA requirements and the current Mechanical Code of New York State. The electrical Phased Electrical demolition of switchgear units and associated equipment. Phased installation of new switchgear units and associated equipment. Phasing details are noted with this specification (see section l.6, I.) and on drawings as well. The work phasing sequence of operation was developed to maintain operation of the Boiler Plant during the construction period. Infection control will be a priority throughout the construction process. Temporary one (1) hour fire-rated or 15 minutes fire-rated plastic barriers will be set up around the work area to prevent dust and debris from spreading to other areas of the hospital. HEPA-filtered negative air machines will be used to maintain negative pressure in the construction zone, ensuring that airborne contaminants are contained. Workers entering the construction zone will be required to pass through an anteroom equipped with HEPA vacuums or wear disposable coveralls that are changed upon exiting. All construction waste will be carefully sealed and removed in accordance with infection control procedures to ensure the cleanliness of the hospital environment. For construction details, please refer to ATTACHMENT IFC VA Stamped Drawings SA Switchgear Replacement 630A17433 11152023 and IFC VA Master Specs SA Switchgear Replacement 630A17433 11152023 FNL 1 as reference. Project Management Platform Requirement Construction contractors and A/E design firms, selected by award to perform work at VISN 2 VA facilities, are required to utilize VISN 2 Autodesk Build Construction management platform, also called Autodesk Construction Cloud (ACC). Access to the platform and training portal will be provided by VISN 2 through project Contracting Officer Representative (COR) at no cost for the duration of the project. Autodesk Build is the management and collaborative environment that VISN 2 uses for all its Non-Recurring Maintenance (NRM), Minor Program projects, Feasibility Studies, Commissioning and Retro-Commissioning contracts.� There is no user, license, or subscription fee to the contractor for using this cloud-based platform. Contractor shall accomplish and complete the following tasks upon award of contract: Request access to ACC platform and Productivity NOW eLearning Site to project VA COR NLT 14 days from contract award. Only staff that shall utilize the platform to be granted access. Examples: Project manager, sub-contractors POC, Site manager, Safety officer, etc. The access request shall be in writing and include a list of staff. The list shall include the following information: Full Name Company Name Email Address Role/Position on the project (i.e., Project manager, site super) Upon granting access, staff shall complete required ACC training through Productivity NOW platform within 12 Calendar days. Upon successful completion of training, contractor shall submit certificates of completion to COR NLT 2 business days. Access to Productivity NOW eLearning will expire after 12 Calendar days after online access is granted. Contractor shall complete ACC training within that period. Additional Staff and Subcontractors can be added at any time with a request submission to the project COR as described above. The contractor shall only use the ACC platform for contract required submissions, official project correspondence to be acknowledged, reviewed, and actioned by the responsible party. No additional time shall be added to the contract, nor an increase in contract amount be provided for the contractor s failure to utilize the ACC platform as the project s official communication and collaboration system. Any correspondence out of platform shall not be the governing authority contradicting direction and will be at the contractor s expense. Official project correspondence and collaboration includes but not limited to: RFIs, submittals, schedules, shutdown requests, actionable tasks, reports, testing, safety inspections, photos, and site surveys. Contractor must inform the COR of any staff changes NLT 2 business days from the change. Staff changes pertain to staff who was granted access to the ACC platform. Contractor shall request termination of access, replacement of personnel and/or any other action that might impact the contractor ability to maintain required utilization of the platform. Contractor submission requirements cannot be accepted for work to begin without meeting all ACC Platform requirements outlined herein, including completing required ACC platform training. General Requirement: The Contractor shall take all necessary precautions and safety measure to protect all patients and end users from all related activities. The Contractor shall test and verify all work to ensure proper operation. The Contractor must have OSHA training, and specialized OSHA training. In the performance of all work, the workers must be incompliance with safety regulations governing worker safety (OSHA: 29 CFR 1926 Safety and Health Regulations for Construction; NFPA, Life Safety Codes, etc.). All work shall be done in accordance with NFPA, Life Safety, VA Standards and Regulations, VA Policy and requirements, OSHA regulations, and manufacturer specification. The Contractor shall guarantee that all work performed will be free from all defects in workmanship and materials and that all installation and repair will provide the capacities and characteristics specified. The contractor shall guarantee that if, during a period of construction from the date of the certificate of completion and acceptance of the work, any such defects shall be repaired by the contractor at his own cost. It is the responsibility of the contractor to verify all quantities, field conditions and measurements prior to starting work. The contractor shall notify the CO/COR and VA Engineering Team of any differing site conditions prior to starting All contractor employees and subcontractors participating under this contract are required to complete the VA's Privacy training requirement - VA Privacy Training for Personnel without Access to VA Computer Systems or Direct Access to or the Use of VA Sensitive Information Contractors must provide certifications of completion to the COR during each year of the contract.� Training expires 365 days after the training is taken.� This requirement is in addition to any other training that may be required of the contractor and subcontractor(s). The COR for the contract is responsible for ensuri

Who won similar work

26 award notices on SAM.gov in the last 24 months. Matched by: Same office (242-NETWORK CONTRACT OFFICE 02 (36C242)), same product/service code (PSC) Y1DA.

Single-winner award sizes (26): middle half $425K to $1.2M, median $760K; range $94K to $10.9M.

WinnerAwardsValueLast
J & J MECHANICAL AND CONSTRUCTION GROUP LLC3$11.7MSep 22, 2026
TACTICAL CONSTRUCTION, INC3$10.7MMay 22, 2026
Frontline Group LLC · $FRO2$2.2MJun 16, 2026
SERVIAM CONSTRUCTION LLC2$2.1MMay 20, 2026
M WILKINSON CONSTRUCTION COMPANY1$7.8MMar 16, 2026
F & C GROUP JV LLC1$1.9MMay 20, 2026
KF GROUP LLC1$988KJun 16, 2026
JETEX MECHANICAL, LLC1$950KMar 11, 2026
BLACKHORSE LLC1$864KMay 13, 2026
LAUBACKER ENTERPRISES, INC.1$861KSep 30, 2025

Value counts new single-winner awards. "Shared" awards are multiple-award contracts that list every winner with the same total ceiling (same contract, or the same office, day and amount); that ceiling is not one company's win, so it is not added in. Contract modifications are not new awards and are not added in either. Notices whose amount is a placeholder such as $999,999,999 are not added in. Revenue next to a ticker is the company's revenue over the latest 12 months in its SEC filings.

Latest awards

Competitive landscape

For the 8 most frequent past winners above. Lobbying is matched by the company's exact name or exact ticker; agencies are as named on the filings.

  • 0 of these past winners lobbied Veterans Affairs, Dept of (VA) since 2024 (0 filings)
  • 0 of their lobbyists list a past Veterans Affairs, Dept of (VA) job
  • No corporate PAC money from them to the overseeing committees since 2024
  • 0 foreign-agent (FARA) registrations
See who and the source records with Pro

Policy around it

Bills the past winners named while lobbying this agency's issues, rules from the department, and executive orders that name the agency, last 12 months.

  • 0 bills named on the past winners' lobbying filings
  • 25 rules from the department in the last 12 months
  • 0 executive orders naming the agency in the last 12 months
See who and the source records with Pro

Market

For past winners matched exactly to a listed company. Insider trades are open-market buys and sells (Form 4) in the last 90 days, shown as facts; our own study found insiders do not reliably buy ahead of awards. A sale marked 10b5-1 was made under a trading plan set up in advance.

  • 1 of the past winners are listed companies
  • 0 insider buys and 0 insider sells at them in the last 90 days
See who and the source records with Pro

Sources: SAM.gov notices and award notices; Senate LDA lobbying filings; FEC filings; FARA; Federal Register; congress.gov; SEC Form 4. Every row above links to its record.

Companies are matched to tickers by exact name, including the subsidiaries a company lists in its SEC filings. A company we could not match shows no market rows; that is a miss, not a finding.