Sources SoughtPosted Dec 12, 2024·Original deadline passed (Feb 8). See latest amendment for current deadline.

Ames High-Rate Composite Manufacturing Facility (AHRCM)

NASA · NASA AMES RESEARCH CENTER

In plain words

NASA is planning to buy "Ames High-Rate Composite Manufacturing Facility (AHRCM)". This is an early notice: it is not taking bids yet. The work is in Moffett Field, CA, USA. The original due date (Feb 8, 2025) has passed; check the latest amendment for the current one. In the last 2 years, similar work went to 3 companies, usually for about $6.9M per award. An award could come any day: the usual time to award has passed.

Put together from the facts on this page; the details and sources are below.

Stage
Early notice (sources sought, presolicitation or special notice)
NAICS
927110
Value
Not stated
Solicitation
80ARC025AHRCM_RFI
Set-aside
None stated
PSC
AR12
Place
Moffett Field, CA, USA
Contact
Alex Mazhari (N210@nasa.onmicrosoft.com)
Loading your pipeline and notes…
CSV Email

Capture briefs (a one-page, shareable copy of this page) are part of Pro. The CSV here holds the notice, its timeline and past awards.

Where this opportunity stands

Every notice posted under solicitation 80ARC025AHRCM_RFI in this department, oldest first.

Early notice
  • Dec 12, 2024 · this notice
    Sources Sought
  • Jan 24, 2025
    Sources Sought
    View
  • Feb 6, 2025
    Sources Sought
    View
Solicitation
None posted
Award
Not yet. Expected award: Any day (median passed). Typical range Feb 8, 2025 to Jul 17, 2025; middle Apr 18, 2025.
Measured from 23 past early notices at National Aeronautics and Space Administration that later posted an award (middle half of cases, counted from Dec 12, 2024).
Held to the response deadline (Feb 8, 2025): no award is forecast before responses are in.

Next steps for this stage

Standard steps for the notice type; not advice about this buyer.

  • Answer the notice: this is when the requirement can still be shaped.
  • Contact the contracting officer named on the notice.
  • Check who won similar work; they are the likely bidders.

What the notice says

NASA Ames Research Center (ARC) is hereby soliciting information from potential sources for manufacturing process development of high-rate composites for aerospace applications. Description The National Aeronautics and Space Administration (NASA) Ames Research Center (ARC), on behalf of the Engineering Directorate and Aeronautics Directorate, is hereby soliciting information from potential sources regarding high-rate thermoplastic manufacturing technologies and process development. NASA is interested in engaging with government, industry, and academia for collaborations to develop thermoset an… (show all)

d thermoplastic manufacturing processes tailored, but not limited, to aerospace applications with the Ames High-Rate Composite Manufacturing Facility (AHRCM). The AHRCM supports the research and development of aerospace materials processes (particularly for thermoplastic composites), modeling, and large structures with the goal of mitigating labor-in-the-loop manufacturing bottlenecks by increasing volumetric fabrication throughput of composites and reducing inertial assembly errors as a virtue of robotic automation. This Request for Information (RFI) serves to solicit organizations that have demonstrated heritage referencing composite materials for aerospace applications, particularly those pertaining to aeronautics, spacecraft, intelligent structures, automotive, and other high-rate thermoset & thermoplastic manufacturing applications. Background The emerging Advanced Air Mobility (AAM) industry must rely heavily on advanced composite materials to build vehicles that will meet the performance and safety requirements needed to achieve commercial success. These electrically powered vertical takeoff and landing (eVTOL) vehicles must make extensive use of light-weight carbon fiber composite structures and components to maximize vehicle range and payload achievable with the energy storage density of foreseeable battery technology. Using conventional metallic materials for this application is not an option because: � Metallic structures are heavy, reducing the achievable vehicle payloads and ranges to impractical levels. � Traditional aircraft production rates, utilizing the current state-of-the-art in materials and production methods approach 1,000 aircraft per year. To be economically feasible, AAM aircraft production rates must reach 5,000 or more aircraft per year. Significant reductions in composite manufacturing costs, large improvements in manufacturing consistency and rates of production, will be required to meet vehicle cost goals and allow mass-produced components to be certified by the FAA. The automotive industry has begun to develop high-rate manufacturing processes for automobiles that achieve significant reductions in manufacturing cost, but these methods have not yet been applied to the manufacture of aerospace components that require very high levels of quality assurance. Ames Research Center developed AHRCM in 2021 as a composite manufacturing facility that specializes in the rapid processing of thermoset Carbon Fiber Reinforced Polymers (CFRP). The facility was created to reduce the time-to-part for aerospace components, using industry-standard High-Pressure Resin Transfer Molding (HP-RTM) and thermoset CFRP thermoforming, also referred to as prepreg �stamp-forming� or �drape-molding.� Located in the high bay of a historic aviation hangar, thermoforming is accommodated by two independent automated manufacturing lines: preforming and final thermoforming. The preforming stage currently contains a 6-DOF ABB Robotics charge loading manipulator, a conductive and infrared heating platen, 20 pneumatic grippers mounted on a shuttling system, a 300-ton press, and a 6-DOF ABB unloading manipulator. This capability was designed for thermoset CFRP preforming, and as such can subject a ~1-foot by 4-foot CFRP prepreg 7-ply charge through ~350C in the preforming platen and ~250C in a preforming drape mold with up to 300 tons of force. The final thermoforming line contains a 6-DOF ABB charge loading manipulator, a 3,600-ton press, a heating system that can heat molds with ~250C via thermal fluid, a 6-DOF ABB unloading manipulator and an HP-RTM capability which can be integrated for compatibility with non-prepreg composites. Ames is particularly interested in collaborating to develop advanced composite modeling and thermoplastic composite manufacturing processes by retrofitting AHRCM�s current thermoforming lines. Thermoplastic CFRP requires elevated temperatures at ~300C - 385C, varying with respect to the specific fiber and resin matrix utilized. Initial feasibility studies and empirical testing demonstrate that AHRCM may be retrofit for compatibility with thermoplastic CFRP, while maintaining the current high-rate automated configuration. Additional information regarding the facility may be referenced at: https://www.nasa.gov/ahrcm/ Requested Information -Descriptions of composite manufacturing techniques utilized, with applications demonstrating developed technical heritage by the interested party. Of particular interest are high-rate, large-scale manufacturing processes for thermoplastic and thermoset materials in aerospace applications. -Non-Metallic materials testing conducted by the interested party, including details referencing developed mechanical properties, material properties, and non-destructive evaluation techniques. -Demonstrated expertise of process development for non-metallic materials. Specific capabilities of interest are line modeling, in-situ process control, and process qualification. -Applications of interest for applying high-rate thermoplastic and thermoset composite manufacturing processes. The National Aeronautics and Space Administration (NASA) ARC is seeking capability statements from all interested parties, including all socioeconomic categories of Small Businesses and Historically Black Colleges and Universities (HBCU)/Minority Institutions (MI), and members of the underserved communities as defined by Executive Order 13985, Advancing Racial Equity And Support For Underserved Communities Through The Federal Government, for the purposes of determining the appropriate level of competition and/or small business subcontracting goals for manufacturing process development of high-rate composites for aerospace applications. The Government reserves the right to consider a Small, 8(a), Women-owned (WOSB), Service Disabled Veteran (SD-VOSB), Economically Disadvantaged Women-owned Small Business (EDWOSB) or HUBZone business set-aside based on responses received. No solicitation exists; therefore, do not request a copy of the solicitation. If a solicitation is released, it will be synopsized on SAM.gov. Interested firms are responsible for monitoring this website for the release of any solicitation or synopsis. Vendors having the capabilities necessary to meet or exceed the stated requirements are invited to submit appropriate documentation, literature, brochures, and references. All responses shall be submitted electronically via email to Alex Mazhari at N210@nasa.onmicrosoft.com and a.mazhari@nasa.gov no later than February 7th, 2025 at 22:00 PST. Please reference AHRCM RFI in any response. This synopsis is for information and planning purposes only and is not to be construed as a commitment by the Government nor will the Government pay for information solicited. Respondents will not be notified of the results of the evaluation.

Who won similar work

4 award notices on SAM.gov in the last 24 months. Matched by: Same agency (NASA), same product/service code (PSC) AR12.

Single-winner award sizes (4): middle half $453K to $13.2M, median $6.9M; range $71K to $13.2M.

WinnerAwardsValueLast
SIERRA SPACE CORP2$26.3MJan 8, 2026
UNIVERSITY OF UTAH Salt Lake City UT 84112 USA1$580KSep 29, 2025
Outpost Technologies, INC1$71KJun 10, 2025

Value counts new single-winner awards. "Shared" awards are multiple-award contracts that list every winner with the same total ceiling (same contract, or the same office, day and amount); that ceiling is not one company's win, so it is not added in. Contract modifications are not new awards and are not added in either. Notices whose amount is a placeholder such as $999,999,999 are not added in. Revenue next to a ticker is the company's revenue over the latest 12 months in its SEC filings.

Latest awards

Competitive landscape

For the 3 most frequent past winners above. Lobbying is matched by the company's exact name or exact ticker; agencies are as named on the filings.

  • 1 of these past winners lobbied Natl Aeronautics & Space Administration (NASA) since 2024 (5 filings)
  • 0 of their lobbyists list a past Natl Aeronautics & Space Administration (NASA) job
  • No corporate PAC money from them to the overseeing committees since 2024
  • 0 foreign-agent (FARA) registrations
See who and the source records with Pro

Policy around it

Bills the past winners named while lobbying this agency's issues, rules from the department, and executive orders that name the agency, last 12 months.

  • 1 bills named on the past winners' lobbying filings
  • 16 rules from the department in the last 12 months
  • 0 executive orders naming the agency in the last 12 months
See who and the source records with Pro

Market

For past winners matched exactly to a listed company. Insider trades are open-market buys and sells (Form 4) in the last 90 days, shown as facts; our own study found insiders do not reliably buy ahead of awards. A sale marked 10b5-1 was made under a trading plan set up in advance.

  • 0 of the past winners are listed companies
  • 0 insider buys and 0 insider sells at them in the last 90 days
See who and the source records with Pro

Sources: SAM.gov notices and award notices; Senate LDA lobbying filings; FEC filings; FARA; Federal Register; congress.gov; SEC Form 4. Every row above links to its record.

Companies are matched to tickers by exact name, including the subsidiaries a company lists in its SEC filings. A company we could not match shows no market rows; that is a miss, not a finding.